Changing State Via a Parallel Transition

If a parallel transition has been created, multiple users must run the transition before the file actually changes state.

This procedure describes how two users send a file back to editing by using a parallel transition to change its state.

  1. User A provides the first approval:
    1. Log in to the vault.
    2. Navigate to the file to be sent back to editing and select it.
    3. Click Modify > Change State > Editing required .

      The Editing required transition indicates the number of users who must run the transition.

      When the Do Transition dialog box appears, the Result column indicates that after this transition is run, one more user must perform the transition before the state of the file is changed.

    4. Ensure that Change state is checked.
    5. Enter a Comment.

      The comment appears in the file's history and in a History column that is added when the transition is run by other users.

    6. If dynamic notifications are enabled for the transition, enter a Notification comment and select the users to notify.

      On a parallel transition, notification comments are not sent until after the file changes state, which is after the required number of users transition the file.

    7. Click OK.

      The State column in the file list shows that the file did not change state.

  2. User B provides the second approval:
    1. Log in to the vault.
    2. Navigate to the file to be sent back to editing and select it.
    3. Click Modify > Change State > Editing required .

      The Editing required transition now indicates that one user has run the transition and that two users must run the transition to change the state of the file.

      When the Do Transition dialog box appears, there are no notes in the Results column, since if User B approves the transition, the required number of approvals has been reached.

      At the bottom of the dialog box, the History field shows the comments made by User A.

    4. Ensure that Change state is checked.
    5. Enter a Comment.
    6. If dynamic notifications are enabled for the transition, enter a Notification comment and select the users to notify.
    7. Click OK.

      The State column in the file list now shows that the file has changed state.



Bu başlık hakkında geribildirimde bulunun

SOLIDWORKS; dokümantasyonun sunumu, doğruluğu ve bütünlüğü hakkında geribildiriminizi almaktan memnuniyet duyar. Bu başlık ile ilgili yorum ve önerilerinizi, aşağıdaki formu kullanarak doğrudan dokümantasyon takımımıza yollayın. Dokümantasyon takımı teknik destek sorularına yanıt veremez. Teknik destek ile ilgili bilgiler için buraya tıklayın.

* Gerekli

 
*Email:  
Konu:   Yardım Başlıkları Hakkında Geribildirim
Sayfa:   Changing State Via a Parallel Transition
*Yorum:  
*   Kişisel Bilgilerimin Dassault Systèmes tarafından kullanılacağının belirtildiği gizlilik politikasını okuduğumu ve kabul ettiğimi onaylıyorum

Yazdırma Başlığı

Yazdırılacak içeriğin kapsamını seçin:

x

Internet Explorer 7'den daha eski bir tarayıcı sürümünü kullandığınızı tespit ettik. Optimize edilmiş görünüm için tarayıcınızı Internet Explorer 7 veya daha yenisine yükseltmenizi öneririz.

 Bu mesajı bir daha asla gösterme
x

Web Yardım İçerik Sürümü: SOLIDWORKS PDM 2014 SP05

SOLIDWORKS içindeki Web yardımını devre dışı bırakmak ve onun yerine yerel yardımı kullanmak için Yardım > SOLIDWORKS Web Yardımını Kullan öğelerine tıklayın.

Web yardımı arabirimi ve araması ile ilgili karşılaştığınız sorunları lütfen yerel destek temsilcinize bildirin. Yardım başlıkları hakkında ayrı ayrı geri bildirimde bulunmak için ilgili başlığın sayfasından "Bu başlık hakkında geribildirim" bağlantısına tıklayın.