The task and its title, scheduled time, scheduled date, and status
appear in the
Tasks panel. The status of
the task is
Scheduled.
To run a scheduled task, your computer and printer must be
on at the scheduled start time. The
SOLIDWORKS
Task Scheduler window does not need to be open. If your
computer is off at the scheduled start time, the task runs when you turn
your computer on.
At the scheduled start time, the task is
initiated. If the task acts on more than one file, a sub-task is
generated for each file. If you selected Backup task files in Task
Options, a backup copy of each file is saved to a
.zip file. Then each file is
printed. When the task completes, the status changes to Completed.
If your backup files include Unicode file paths, use a zip
file extraction application that supports UTF-8
encoding.