If you receive a revised drawing for a
previously-created
inspection project, you can replace the existing drawing in the project. Then you can
capture the incremental changes between the drawings and export the project to a new
ballooned PDF and inspection report.
You can only replace an entire drawing, not individual characteristics.
To replace
drawings:
-
In the
existing project, click Replace Drawing
(Document ribbon).
-
In the dialog box, open the revised drawing.
-
Click Yes or No to
choose whether
to compare the revised drawing to the existing drawing.
If you click
Yes,
the drawings are compared, and you need to click
![](djd1654009499378.image)
in the
Properties/Preferences
PropertyManager to replace the drawing. If you click
No, the drawing is replaced.