Default |
Sets the default fillet bead to be used for all fillet beads found in the part. |
Weld Type |
Sets the name of the weld type, for example, Aluminum Bead. Weld type includes the bead type and material. |
Cost Per Volume |
Sets the cost per volume of the fillet bead. Weld beads use cost per length, while fillet beads use cost per volume.
|
Machine Cost |
Sets the Machine Cost associated with the operation. |
Labor Cost |
Sets the Labor Cost associated with the operation. |
Operation Setup Time |
Sets the amount of time it takes to set up a machine for each operation. Setup cost = Operation Setup time * (Machine Cost + Labor Cost)
|
Setup Distribution |
Sets how to distribute the Setup Cost:
Divided Over Total Quantity
|
Setup cost is divided by the total number of parts (Setup cost per part = Setup cost / Total number of parts). For example, if the setup cost is 100 and the total number of parts is 100, then the setup cost per part is 1.
|
Divided Over Lot Size
|
Setup cost is divided by the lot size (Setup cost per part = Setup cost / Lot size). For example, if the setup cost is 100 and the lot size is 10, then the setup cost per part is 10.
|
Applied Once Per Part
|
Setup cost is applied per part
(Setup cost per part = Setup cost). For example, if the setup cost is 100 then the setup cost per part is 100.
|
|