Machines |
Sets the name of the machine. |
Mill, Turn, and Drill |
Sets the machine as a milling, turning, or drilling machine. |
Machine Cost |
Sets a cost per hour to use the machine. |
Labor Cost |
Sets a cost per hour for an operator to use the machine. |
Max RPM (rev/min) |
Sets a value to be used when the calculated RPM is greater than the maximum RPM for material removal rate (MRR) calculations. The MRR equation displayed in the templates is a base equation. Some manufacturing processes require additional values to determine the total MRR. As a result, the calculated MRR value might not match the value shown equation in all calculations, depending on the manufacturing processes assigned in the template.
|
Load/Unload Time |
Specifies the time it takes to load a part into a machine and then unload it for each setup operation. |
Operation Setup Time |
Specifies the time it takes to set up fixtures and other machining process setup operations. |
Setup Distribution |
Specifies options for applying the operation setup time to costing:
Applied Once Per Part
|
|
Divided Over Total Quantity
|
|
Divided Over Lot Size
|
|
|